Power outages on Monday, September 11

There will be a sitewide (except for the Village residences and labs) power outage on Monday, September 11, as our electrical team switches site power distribution from the Master Substation to the Kautz Road Substation. 

The electrical outage will begin at 6:00 AM with the powering down of the Main Injector Areas; these areas will be powered ON by 6:25 AM. 

This will be followed by an electrical outage for the remainder of the site (except for the Village residences and labs ).  This outage is planned for 6:30 AM and will end around 7:00 AM.
 
This outage will affect central heating/cooling utility services that originate from the Central Utility Building (CUB) as well.  In order to have a controlled (and more friendly) shutdown of the heavy equipment at CUB, it will begin shutdown at 6:00 AM and will be started back up again as soon as site power is restored.