The steel work and metal deck installation for the future IARC OTE building is well under way. Photo: Cindy Arnold

Barton Malow Construction Company is well under way with the steel work and metal deck installation for the IARC Office, Technical and Education Building. The first phase of the steel work is for Ground Floor West, which will house the main entrance lobby, 175-seat lecture hall, executive conference room and light tech space. Columns for the second- and third-floor office spaces are also quickly going up. Much of this steel structure will remain exposed within the building. While steel work proceeds on the west part of the building, underground foundations and the elevator pit are being completed on the east side in front of CDF.

You can view more photos of IARC construction progress at the IARC OTE Facebook page.