Concrete pouring has begun for the new MC-1 building. Photo: Cindy Arnold |
Workers from Whittaker Construction & Excavating Inc. began pouring the basement slab of the new MC-1 building on June 27. Seven-hundred cubic yards of concrete and 90 concrete trucks were required to complete the concrete pour. The slab is the basement floor that will support the future 700-ton Muon g-2 experiment’s storage ring.