Main Injector:
FESS worked with contractors to replace surge arrestors at the Kautz Road Substation.
Main Injector experts turned on power supplies, established ramps and established 8-GeV beam in the Main Injector. They subsequently established 120-GeV beam, smoothed the beam orbits during ramp-up and tuned the abort line.
NuMI:
Main Injector experts extracted low-intensity beam to the NuMI beamline. NuMI experts started tuning it up for horn scans.
View the AD Operations Department schedule.