Press release

Some assembly required: Scientists piece together the largest U.S.-based dark matter experiment

Major deliveries in June set the stage for the next phase of work on LUX-ZEPLIN project, led by Lawrence Berkeley National Laboratory. A Fermilab group is responsible for implementing key parts of the critical systems that handle the xenon in the detector.

Media contact

Below is a press release issued by Lawrence Berkeley National Laboratory on the start of the next phase of work for the LUX-ZEPLIN project. A Fermilab group led by Hugh Lippincott, currently a Fermilab scientist who will join the University of California, Santa Barbara, in the fall, and Eric Dahl, a joint appointee and associate professor at Northwestern University, is responsible for implementing key parts of the critical systems that handle the xenon in the LUX-ZEPLIN detector. These include the heat exchange system that allows the entire 10-ton xenon target to be purified every 2.3 days, as well as the controls system that safeguards the greater than $10 million xenon payload in emergency scenarios. View the original Berkeley Lab press release on their news site.

Major deliveries in June set the stage for the next phase of work on LUX-ZEPLIN project

Most of the remaining components needed to fully assemble an underground dark matter-search experiment called LUX-ZEPLIN (LZ) arrived at the project’s South Dakota home during a rush of deliveries in June.

When complete, LZ will be the largest, most sensitive U.S.-based experiment yet that is designed to directly detect dark matter particles. Scientists around the world have been trying for decades to solve the mystery of dark matter, which makes up about 85% of all matter in the universe though we have so far detected it only indirectly through observed gravitational effects.

The bulk of the digital components for LZ’s electronics system, which is designed to transmit and record signals from ever-slight particle interactions in LZ’s core detector vessel, were among the new arrivals at the Sanford Underground Research Facility (SURF). SURF, a former gold mine now dedicated to a broad spectrum of scientific research, was also home to a predecessor search experiment called LUX.

A final set of snugly fitting acrylic vessels, which will be filled with a special liquid designed to identify false dark matter signals in LZ’s inner detector also arrived at SURF in June.

photomultiplier tubes

This picture shows an array of photomultiplier tubes that are designed to detect signals occurring within LZ’s liquid-xenon tank. Photo: Matt Kapust/SURF

Also, the last two of four intricately woven wire grids that are essential to maintain a constant electric field and extract signals from the experiment’s inner detector, also called the time projection chamber, arrived in June (see related article).

“LZ achieved major milestones in June. It was the busiest single month for delivering things to SURF — it was the peak,” said LZ Project Director Murdock Gilchriese of the Department of Energy’s Lawrence Berkeley National Laboratory (Berkeley Lab). Berkeley Lab is the lead institution for the LZ project, which is supported by an international collaboration that numbers about 37 participating institutions and about 250 researchers and technical support crew members.

“A few months from now all of the action on LZ is going to be at SURF — we are already getting close to having everything there,” Gilchriese said.

“We’ve been collectively preparing for these deliveries for some time and everything has gone very well,” said Mike Headley, executive director at SURF. “It’s been exciting to see the experiment assembly work progress, and we look forward to lowering the assembled detector a mile underground for installation.”

All of these components will be transported down a shaft and installed in a nearly mile-deep research cavern. The rock above provides a natural shield against much of the constant bombardment of particles raining down on the planet’s surface that produce unwanted “noise.”

LZ components have also been painstakingly tested and selected to ensure that the materials they are made of do not themselves interfere with particle signals that researchers are trying to tease out.

LZ is particularly focused on finding a type of theoretical particle called a weakly interacting massive particle or WIMP by triggering a unique sequence of light and electrical signals in a tank filled with 10 metric tons of highly purified liquid xenon, which is among Earth’s rarest elements. The properties of xenon atoms allow them to produce light in certain particle interactions.

Proof of dark matter particles would fundamentally change our understanding of the makeup of the universe, as our current Standard Model of physics does not account for their existence.

Assembly of the liquid-xenon time projection chamber for LZ is now about 80% complete, Gilchriese said. When fully assembled later this month, this inner detector will contain about 500 photomultiplier tubes, which are designed to amplify and transmit signals produced within the chamber.

Once assembled, the time projection chamber will be lowered carefully into a custom titanium vessel already at SURF. Before it is filled with xenon, this chamber will be lowered to a depth of about 4,850 feet. It will be carried in a specially designed frame that is designed to minimize vibrations and then floated into the experimental cavern across a temporarily assembled metal runway on air-pumped pucks known as air skates.

Finally, it will be lowered into a larger outer titanium vessel, already long underground, to form the final vacuum-insulated cryostat needed to house the liquid xenon.

That daylong journey, planned in September, will be a nail-biting experience for the entire project team, noted Berkeley Lab’s Simon Fiorucci, LZ deputy project manager.

“It will certainly be the most stressful — this is the thing that really cannot fail. Once we’re done with this, a lot of our risk disappears, and a lot of our planning becomes easier,” he said, adding, “This will be the biggest milestone that’s left besides having liquid xenon in the detector.”

Project crews will soon begin testing the xenon circulation system, already installed underground, that will continually circulate xenon through the inner detector, further purify it, and reliquefy it. Fiorucci said researchers will use about 250 pounds of xenon for these early tests.

Work is also nearing completion on LZ’s cryogenic cooling system that is required to convert xenon gas to its liquid form.

LZ digital electronics, which will ultimately connect to the arrays of photomultiplier tubes and enable the readout of signals from particle interactions, were designed, developed, delivered and installed by University of Rochester researchers and technical staff at SURF in June.

“All of our electronics have been designed specifically for LZ with the goal of maximizing our sensitivity for the smallest possible signals,” said Frank Wolfs, a professor of physics and astronomy at the University of Rochester who is overseeing the university’s efforts.

He noted that more than 28 miles of coaxial cable will connect the photomultiplier tubes and their amplifying electronics — which are undergoing tests at UC Davis — to the digitizing electronics. “The successful installation of the digital electronics and the online network and computing infrastructure in June makes us eager to see the first signals emerge from LZ,” Wolfs added.

Also in June, LZ participants exercised high-speed data connections from the site of the experiment to the surface level at SURF and then to Berkeley Lab. Data captured by the detectors’ electronics will ultimately be transferred to LZ’s primary data center, the National Energy Research Scientific Computing Center (NERSC) at Berkeley Lab via the Energy Sciences Network (ESnet), a high-speed nationwide data network based at Berkeley Lab.

The production of the custom acrylic tanks (see related article), which will contain a fluid known as a liquid scintillator, was overseen by LZ participants at University of California, Santa Barbara.

“The last five tanks, delivered in June, were fabricated using a novel acrylic molding process to closely fit around the cryostat vessel,” said Harry Nelson, professor of physics at UC Santa Barbara.

“The partnership between LZ and SURF is tremendous as evidenced by the success of the assembly work to date,” Headley said. “We’re proud to be a part of the LZ team and host this world-leading experiment in South Dakota.”

NERSC and ESnet are DOE Office of Science User Facilities.

Major support for LZ comes from the DOE Office of Science, the South Dakota Science and Technology Authority, the U.K.’s Science & Technology Facilities Council, and by collaboration members in the U.S., U.K., South Korea, and Portugal.

###

DOE’s Office of Science is the single largest supporter of basic research in the physical sciences in the United States, and is working to address some of the most pressing challenges of our time. For more information, please visit energy.gov/science.

Founded in 1931 on the belief that the biggest scientific challenges are best addressed by teams, Lawrence Berkeley National Laboratory and its scientists have been recognized with 13 Nobel Prizes. Today, Berkeley Lab researchers develop sustainable energy and environmental solutions, create useful new materials, advance the frontiers of computing, and probe the mysteries of life, matter, and the universe. Scientists from around the world rely on the Lab’s facilities for their own discovery science. Berkeley Lab is a multiprogram national laboratory, managed by the University of California for the U.S. Department of Energy’s Office of Science.

The Sanford Underground Research Facility’s mission is to enable compelling underground, interdisciplinary research in a safe work environment and to inspire our next generation through science, technology, engineering, and math education. For more information, please visit the Sanford Lab website at http://www.sanfordlab.org.